The
end of the Pier Restoration is nigh! I have recently received
correspondence from the charity that reflects upon the achievements
of the last two years, which goes something like this...
Around
70% of the high-level steelwork has been replaced, which took the
form of 320 trusses and 850 deck beams. Over 400 new bull rails and
nearly 700 sets of cross bracing have been installed.
In
all some 3,000 tonnes of new steel has been fixed. In addition, all
of the timber has been completely renewed. There are 50 miles of new
deck boards fixed with half a million screws. The boards are built on
18 miles of joists fixed with 12,000 bolts; all 1,000 tonnes of Ekki
timber is from 100% sustainable resources.
There
have been many different companies involved with the Construction;
the majority of these have been local organisations. FPE steelworkers
and TimberCraft carpenters have formed the backbone of the labour
force throughout. The other contractors and specialists have been
here as needed to give a typical labour strength of 50-60 people. In
all, though, over 400 people have worked on the Pier, and each has
played a valuable part in getting it to where it is today.
As
there was only limited access before work started, knowledge of the
structure was limited and, therefore, a lot of assumptions had to be
made about the condition of the structure. In reality, things were
worse than originally assumed, and more steelwork needed to be
replaced.
Furthermore,
poor weather conditions had to be contended with, in particular,
damage caused to the structure by storms in February 2014. Even now,
the weather is very influential; the constant high winds over the
past six weeks have severely restricted operations at the Pier Head.
Only the last twelve trusses still need to be installed, and a couple
of calmer weeks will enable this work to be completed.
The
Visitor Centre is near to completion inside, and outside the cladding
with old deck boards is progressing well. The arena seating on the
North end is now being constructed and the glass balustrade will
shortly be fixed around the roof. Fitting of the Old Bandstand
Pavilion for the new restaurant is underway. Everything is now in the
final stages heading towards completion with a 'gala celebration' planned for May 2016, great stuff!
See website for more information.